REMEDIES FOR BREACH OF CONTRACT
REMEDIES FOR BREACH OF
CONTRACT
When one of the parties
makes a breach of contract, the following remedies are available to the other
party:
1. Damages: Remedy by way
of damages is the most common remedy available to the injured party. This
entitles the injured party to recover compensation for the loss suffered by him
due to the breach of contract, from the party who causes the breach. Sections 73
to 75 incorporate the provisions in this regard.
2. Quantum Meruit: When
the injured party has performed a part of his obligation under the contract
before the breach of contract has occurred, he is entitled to recover the value
of what he has done, under this remedy.
3. Specific Performance
and injunction: Sometimes a party to the contract instead of recovering damages
for the breach of contract may have recourse to the alternative remedy of
specific performance of the contract, or an injunction restraining the other
party from making a breach of the contract. Provisions regarding these remedies
are contained in the Specific Relief Act, 1963.
The first two remedies
stated above are being discussed in some detail,
1. DAMAGES
Section 73 of the Indian
Contract Act, 1872, makes the following provision regarding the right of the
injured party to recover compensation for the loss or damage which is caused to
him by the breach of contract. When a contract has been broken, the party who
suffers by such breach is entitled to receive, from the party who has broken
the contract, compensation for any loss or damage caused to him thereby, which
naturally arose in the usual course of things from such breach, or which the
parties knew, when they niade the contract, to be likely to result from the
breach of it. Such compensation is not to be given for any remote and indirect loss
or damage sustained by reason of the breach.
Compensation for failure
to discharge obligation resembling those created by contract. When an
obligation resembling those created by contract has been incurred and has not
been discharged, any person injured by the failure to discharge it is entitled
to receive the same compensation from the party in default, as if such person
has contracts to discharge it and had broken his contract. Explanation. In
estimating the loss or damage arising from a breach of contract, the means
which existed of remedying the inconvenience caused by the non-performance of
the contract must be taken into account." The Section has been explained
with the help of the following illustrations:
(a) A contracts to sell
and deliver 50 maunds of saltpetre to B, at a certain price to be paid on
delivery. A breaks his promise. B is entitled to receive from A, by way of
compensation, the sum, if any, by which the contract price falls short of the
price for which B might have obtained 50 maunds of saltpetre of like quality at
the time when the saltpetre ought to have been delivered.
(b) A hires B's ship to
go to Bombay, and there take on board, on the first of January, a cargo which A
is to provide and to bring it to Calcutta, the freight to be paid when earned.
B's ship does not go to Bombay, but A has opportunities of procuring suitable
conveyance for the cargo upon terms as advantageous as those on which he had
chartered the ship. A avails himself of those opportunities, but is put to
trouble and expense in doing so. A is entitled to receive compensation from B
in respect of such trouble and expense.
(c) A contracts to buy
from B, at a stated price, 50 maunds of rice, no time being fixed for delivery.
A afterwards informs B that he will not accept the rice if tendered to him. B
is entitled to receive from A by way of compensation, the amount, if any, by
which the contract price exceeds that which B can obtain for the rice at the
time when A informs that he will not accept it.
1. Remoteness of Damage
The following statement
of Alderson B, in the case of Hadley v. Baxendale' is considered to be the
basis of the law to determine whether the damage is the proximate or the remote
consequence of the breach of contract:
"Where two parties
have made a contract which one of them has broken, the damages which the other
party ought to receive in respect of such breach of contract should be such as
may fairly and reasonably be considered either arising naturally, i.e.,
according to the usual course of things, from such breach of contract itself, or
such as may reasonably be supposed to have been in the contemplation of both
the parties, at the time they made the contract, as the probable result of the
breach of it."
The provision contained
in Section 73 (para 1) is similar to rule contained in the above stated
judgment in Hadley v. Baxendale.
The rule in Hadley v.
Baxendale consists of two parts. On the breach of a contract such damages can
be recovered :-
(1) as may fairly and
reasonably be considered arising naturally, i.e., according to the usual course
of things from such breach; or,
(2) as may reasonably be
supposed to have been in the contemplation of both the parties at the time they
made the contract.
In either case, it is
necessary that the resulting damage is the probable result of the breach of
contract.
The principle stated in
the two branches of the rule is virtually the rule of "reasonable
foresight". The liability of the party making the breach of contract
depends on the knowledge, imputed or actual, of the loss likely to arise in case
of breach of contract: The first Enter branch of the rule allows damages for
the loss arising naturally, i in the usual course of things from the breach.
The parties are deemed know about the likelihood of such loss. The second
branch of the rule deals with the recovery of more loss which results from the
special circumstances of the case. Such loss is recoverable, if the possibility
of the same was actually within the knowledge of the parties, particularly who
makes a breach of the contract, at the time of making of the contract. (1)
First branch of the rule in Hadley v. Baxendale: arising in the usual course of
things Damage
Under this branch of the
rule, compensation can be claimed for any loss or damage that arose in usual
course of things from the breach of contract. If the loss is one which does not
arise in the usual course of things but is special loss arising out of special
circumstances, then the situation would be covered by the second branch of the
rule. In that case the loss can be claimed if the same was in the contemplation
of both the parties at the time of making of the contract.
In Hadley v. Baxendale,'
the facts were as under: plaintiff's mill had been stopped due to the breakage
of a crankshaft. The broken shaft had to be sent to the makers at Greenwich as
a pattern for preparing the new one. The defendants, who were common carriers,
agreed to carry the broken shaft to Greenwich. The only information given to
the carriers was that the article to be carried was the broken shaft of a mill
and the plaintiffs were the millers of that mill. Owing to the defendants'
negligence, the delivery of the shaft was delayed. Due to this delay, the mill
remained stopped for a longer time than it would have been, had the shaft been
delivered at Greenwich without any delay. plaintiffs brought an action to
recover damages for the loss of profits arising out of the delay.
It was held that it could
not be contemplated that the mill would be stopped in the usual course of
things, by sending the shaft, as the millers might have another shaft in reserve.
Moreover, the special circumstances were not communicated by the plaintiffs to
the defendants. The plaintiffs were, therefore, not entitled to recover the loss.
It was observed;
It is obvious that, in
great multitude of cases of millers sending off broken shafts to third persons
by a carrier under ordinary circumstance, such consequences would not, in all
probability, have occurred, and these special circumstances were here never
communicated by the plaintiffs to the defendants. It follows, therefore, that
the loss of profit here cannot reasonably be considered such a consequence of
the breach of contract as could have been fairly and reasonably contemplated by
both the parties when they made this contract. For such loss would neither have
flowed naturally from the breach of this contract in the great multitude of
such cases occurring under ordinary circumstances nor were the special
circumstances, which perhaps, would have made it a reasonable and natural
consequence of such breach of contract, communicated to or known by the
defendants.
(2) Second branch of the
rule in Hadley v. Baxendale : More loss arising from the special circumstances
If the loss on the breach
of a contract does not arise naturally, i.e., according to the usual course of
things but it arises due to some special circumstances, the person making the
breach of contract can be made liable for the same provided that those special
circumstances were brought to his knowledge at the time of making the contract.
If he had no knowledge of the special circumstances which result in the
particular loss, he cannot be made liable for the same.
2. Measure of Damages
After it has been
established that a certain consequence of the breach of contract is proximate
and not remote and the plaintiff deserves to be compensated for the same, the
next question which arises is: What is the measure of damages, for the same, or
in other words, the problem is of the assessment of compensation for the breach
of contract.
Damages are compensatory
in nature. The object of awarding damages to the aggrieved party is to put him
in the same position in which he would have been if the contract had been
performed. are, therefore, assessed on that basis. If a party takes security deposit
from the other for the due performance of the contract, he is not entitled to
forfeit the deposit on the ground of default, when no harm is caused to him on
account of such default.
Liquidated damages and
penalty
Sometimes, the parties to
a contract, at the time of making the contract agree to the amount of
compensation payable in the event of the breach of contract. The amount of
compensation payable, which has been agreed beforehand, may be either
liquidated damages or penalty. If the compensation to be paid on the breach of
contract is the genuine pre-estimate of the prospective damages, it is known as
liquidated damages If the compensation agreed to be paid in the event of breach
of contract is excessive and highly disproportionate to the likely loss, viz.,
the amount is fixed in terrorem, with a view to discouraging breach of
contract, it is known as penal Whether a stipulation was penalty or, liquidated
damages depended on the construction of contract to be judged as at the time it
was made, and mere description as penalty or liquidated damages though relevant
was not decisive.
The distinction between
penalty and liquidated damages was thus explained by Lopes, J in Law v.
Redditch Local Board²: The distinction between penalties and liquidated damages
depends on the intention of the parties be gathered from the whole of the
contract. If the intention is to secure performance of the contract by the
imposition of a fine or penalty, then the sum specified is penalty; but if, on
the other hand, the intention is to assess the damages for breach of the
contract, it is liquidated damages.
According to English law)
if the amount of compensation agreed to by the parties is by way of liquidated
damages, the plaintiff will be entitled to recover the agreed amount of
compensation, neither more nor less than that, without the plaintiff having to
prove the exact amount of loss suffered by him by the breach of contract. On
the other hand, if the compensation agreed upon is in the nature of penalty,
the plaintiff will be indemnified to the extent of the actual loss suffered by
him. The fixed by way of penalty is the maximum limit damages, rather than
making a pre-estimate of cases without proof of actual loss.
In the instant case, the
defendant called upon the plaintiff to execute some work but the plaintiff was
not allowed to execute the work by the Executive Engineer. To the claim of Rs.
50,500/- as damages, made by the plaintiff, the Hon'ble High Court awarded Rs.
25,000/- as the plaintiff could not produce sufficient evidence to ascertain
his actual
Holt C.J in Ashby v.
White, observed: Every injury imports a damage though it does not cost the party
one far thing Taking support from the above famous dictum of Holt, C.J., the
High Court said that nominal damages might be awarded where the fact of the
loss was shown but the necessary evidence as to its amount was not given.
Entitlement of
compensation for breach of contract
Section 74 of the Indian
Contract Act, 1872 emphasizes that in case of breach of contract, the party
complaining of the breach is entitled to receive reasonable compensation
whether or not actual is proved to have been caused by such breach. Therefore,
the emphasis is on reasonable compensation. If the compensation named in the
contract is by way of penalty, consideration would be different and the party
is only entitled to reasonable compensation for the loss suffered. But if the
compensation named in the contract for such breach is genuine pre-estimate of
the loss which the parties knew when they made the contract to be likely to
result from the breach of it, there is no question of proving such loss or such
party is not required to lead evidence to prove actual loss suffered by him.
Burden is on the other party to lead evidence for proving that no loss likely
to occur by such breach.
When the parties agree to
the amount of compensation payable in the event of the breach of contract, the
position in India is governed by the following provision contained in Section
74 of the Indian Contract Act: "74. Compensation for breach of contract
where penalty stipulated for.-Where a contract has been broken, if a sum is named
in the contract as the amount to be paid in case of such breach, or if the
contract contains any other stipulation by way of penalty, the party
complaining of the breach is entitled, whether or not actual damage or loss is
proved to have been caused thereby, to receive from the party who has broken
the contract, reasonable compensation not exceeding the amount so named or, as
the ce may be, the stipulated for. Explanation-A stipulation for increased
interest from the date o default may be a stipulation by way of penalty.
Exception. When any person enters into any bail bond recognizance or other
instrument of the same nature or, under the provisions of any law, or under the
orders of the Central Government or any State Government, gives any bond for
the performance of any public duty or act in which the public interested, he
shall be liable, upon breach of the condition of such instrument, to pay the
whole sum mentioned therein.
Explanation-A person who
enters into a contract with the Government does not necessarily thereby
undertake any public duty, or to do an act in which the public are interested. The
rule contained in Section 74 provides that when the parties have mentioned in
the agreement the amount of compensation to be paid in the event of breach, the
injured party is entitled to receive the party who has broken the contract
reasonable compensation not exceeding the amount named in the contract. This is
the rule regardless of the fact whether the sum agreed to be paid is by way of
liquidated damages or penalty. It means that the amount of compensation, if pre-determined
by the parties, is the maximum which the injured party can receive. Mention of
specific amount of compensation does not necessarily entitle the plaintiff to
claim that sum, but the actual amount is to be determined by the Court. The
Court, however, cannot award higher damages than agreed upon. For example, A
gives B a bond for the repayment of Rs. 1,000 with interest at 12 per cent at
the end of six months, with a stipulation that, in case of default, interest
shall be payable at the rate of 75 per cent from the date of default. This is a
stipulation by way of penalty, and B is only to recover from A such
compensation as the Court considers reasonable.2
2. QUANTUM MERUIT
Ordinarily, if a person,
having agreed to do some work or render some services, has done only a part of
what he was required to do, he cannot claim anything for what he has done. When
a person agrees to complete some work for a lump sum, non-completion of the
work does not entitle him to any remuneration even for the part of the work
done. But the law recognizes an important exception to this rule by way of an
action for 'Quantum Under this action, if A and B have entered into a contract,
and A, who has already performed a part of the contract, is then prevented by B
from performing the rest of his obligation under the A can recover from B
reasonable remuneration for whatever he has already done.
The essentials of an
action of quantum meruit are as follows:
1. One of the parties
makes a breach of contract, or prevents the performance of it by the other side.
2. The party injured by
the breach of the contract, who has already performed a part of it, elects to
be discharged from further performance of the contract and brings an action for
recompense for the value of the work he has already done.
For instance, if A agrees
to deliver B 500 bags of wheat and when A has already delivered 100 bags, B
refuses to accept any further supply, A can recover from B the value of wheat
which he has already delivered.
Comments
Post a Comment